Harper Center Renovation Updates — Aug. 29

Renovations in the Mike and Josie Harper Center continue.

Please note, there may be changes due to the construction schedule as renovations progress. Continue to watch Creighton Today for updates.

Upcoming Construction and News

  • Demolition has started for the former bookstore location, with some noisy construction and vibrations throughout the building anticipated.
  • Designs on the campus chapel and Enrollment Management office are underway.
  • Planning has begun for the Harper Center Starbucks, with an opening anticipated in spring 2020.
  • Temporary walls have been installed in the atrium for the new Career Center location.

Previous Moves

  • July 26 — Card Services will be temporarily relocating from its location, Room 1094, on the first floor to Room 2067.
  • JayClean and the Mother’s Room (Lactation Room), located on the north end of the first floor, will be offline temporarily as their new spaces are built out.
  • July 30— BrewJay will close its current location on the second floor. On Aug. 5, it will reopen in the front area of the Harper Dining Hall on the first floor.
  • The Creighton Bookstore is now located in the Murphy Building. It is scheduled to move back into the Harper Center over spring break 2020 on the lower level near the east entrance.
  • Student Counseling has located to the first floor of Markoe Hall, just west of the Vinardi Center (Old Gym), sharing space with the new Health Education and Compliance Office.
  • The Schlegel Center for Service and Justice (SCSJ) has moved to Becker Hall.
  • The Reservations Office has moved to Swanson Hall Room 124.
  • The east curbside drop-off lane permanently closed with the beginning of construction. The east entrance remains open for pedestrian use.

 

 